Filters
Question type

Study Flashcards

Start-to-finish relationships are the most frequently used dependencies between activities.

A) True
B) False

Correct Answer

verifed

verified

Network diagrams are the preferred technique for showing activity sequencing.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is true of a finsih-to-finish dependency?


A) It is a dependency in which the "from" activity cannot start until the "to" activity or successor is started.
B) It is a dependency in which in which the "from" activity must finish before the "to" activity or successor can start.
C) It is a dependency in which the "from" activity must be finished before the "to" activity can be finished.
D) It is a dependency in which the "from" activity must start before the "to" activity can be finished.

E) A) and C)
F) All of the above

Correct Answer

verifed

verified

In a Gantt chart, thick black bars represent milestones achieved in a project.

A) True
B) False

Correct Answer

verifed

verified

Which of the following documents is most likely to include planned project start and end dates which serve as the starting points for a detailed schedule?


A) Resource breakdown structure
B) Milestones list
C) Organizational process assets update
D) Project charter

E) B) and C)
F) A) and B)

Correct Answer

verifed

verified

The main outputs of _____ include work performance measurements, organizational process assets updates, and project document updates.

Correct Answer

verifed

verified

A drawback of the precedence diagramming method is that it cannot be used unless dummy activities are employed.

A) True
B) False

Correct Answer

verifed

verified

A schedule management plan includes information which describes the format and frequency of schedule reports required for the project.

A) True
B) False

Correct Answer

verifed

verified

Duration estimates can be provided as a discrete number, a range, or as a(n) _____.

Correct Answer

verifed

verified

three-poin...

View Answer

Describe critical path analysis. How is the critical path calculated?

Correct Answer

verifed

verified

Critical path analysis is a network diag...

View Answer

In project time management, the primary output of defining activities is a schedule management plan.

A) True
B) False

Correct Answer

verifed

verified

The amount of time an activity can be delayed without delaying the early start date of any immediately following activities is known as a _____.


A) forward pass
B) backward pass
C) fast tracking
D) free slack

E) A) and C)
F) C) and D)

Correct Answer

verifed

verified

Which of the following processes in project time management involves identifying the specific tasks that the project team members and stakeholders must perform to produce the project deliverables?


A) Defining activities
B) Sequencing activities
C) Developing the schedule
D) Estimating activity durations

E) A) and B)
F) None of the above

Correct Answer

verifed

verified

In a(n) _____ relationship, the "from" activity must start before the "to" activity can be finished.

Correct Answer

verifed

verified

In a critical path analysis, the shortest path is what drives the completion date for the project.

A) True
B) False

Correct Answer

verifed

verified

A hierarchical structure that identifies the project's resources by category and type is known as a(n) _____.

Correct Answer

verifed

verified

resource b...

View Answer

One of the first reality checks on scheduling that a project manager should make is to review the _____.

Correct Answer

verifed

verified

_____ have no duration and no resources but are occasionally needed on AOA network diagrams to show logical relationships between activities.

Correct Answer

verifed

verified

To define activities, the project team should start with reviewing the schedule management plan, scope baseline, enterprise environmental factors, and organizational processes.

A) True
B) False

Correct Answer

verifed

verified

_____ occurs when a resource works on more than one task at a time.

Correct Answer

verifed

verified

Showing 21 - 40 of 100

Related Exams

Show Answer